Rampal to turn into Tk 2,498cr solar power plant

Published October 26, 2026 · Updated October 26, 2026 · By Sandra Anderson - thebangladaily.com

Foto : Sandra Anderson - thebangladaily.com

Rampal Site Set for Major 442MW Solar Expansion

Thebangladaily.com – Bangladesh is preparing to convert land once earmarked for coal-based power generation into one of its largest renewable energy facilities, with plans advancing for a 442-megawatt solar power plant in Rampal.

The Bangladesh Power Development Board, or BPDB, expects to seek tenders for the project after completing the required documents. Construction is planned to begin next year, while full commercial operation is targeted for June 2029. The project has an estimated cost of Tk 2,498.08 crore.

Located in Rampal, the proposed grid-connected facility would add a substantial volume of renewable electricity to the national system. It would also sit beside the existing 1,320MW Maitree Super Thermal Power Plant, creating a visible contrast between Bangladesh’s established fossil-fuel infrastructure and its growing investment in cleaner generation.

From Reserved Coal Land to Solar Generation

The solar project will be developed on Block-B, a 918.50-acre tract held by BPDB. The land formed part of a wider 1,834-acre acquisition made in 2012 for coal-power development. Block-A was later used for the Maitree Super Thermal Power Plant, while Block-B remained available for future use.

That unused portion is now being repositioned for renewable generation. The change reflects a broader effort to increase solar capacity while reducing reliance on imported fossil fuels and limiting environmental pressure around the Sundarbans, the world’s largest mangrove forest.

Engineer Rezaul Karim, chairman of BPDB, said work is under way to prepare tender documents after the Executive Committee of the National Economic Council approved the project on Saturday.

The plant is designed with 442 megawatt-peak solar capacity and an eight-hour battery storage system. Storage will be important because solar electricity production changes with daylight and weather conditions. By retaining energy for later use, the system is intended to support a steadier supply when solar panels are not producing at full output.

Grid Connection and Regional Impact

A new 230-kilovolt transmission arrangement will connect the facility to Bangladesh’s national grid. Once operational, the plant would provide 442MW of electricity to a system serving the Khulna division and other connected areas.

Khulna’s peak electricity demand reached 1,972MW on a day in October 2026. A solar facility of this scale would therefore represent a meaningful addition to the regional supply mix, particularly during periods when daylight generation is available.

The project could also reduce the need for expensive power support measures and lower dependence on fossil-fuel-based electricity in the region. Imported fuel prices and supply conditions can place pressure on power-sector costs, making locally generated renewable electricity an increasingly important consideration for long-term planning.

BPDB expects the plant to produce electricity at a tariff of Tk 6.18 per unit. That figure is significantly below the estimated Tk 8.87 per unit tariff for another proposed solar project in Sonagazi, a difference of nearly 30 percent.

Financing and Core Equipment

The financing plan combines BPDB resources with support from the Power Sector Development Fund. BPDB is expected to provide Tk 374.71 crore from its own funds, while Tk 2,123.37 crore would come from the PSDF at a 2 percent interest rate.

Solar modules and mounting structures account for the largest share of planned spending, with an allocation of Tk 1,238.61 crore. Electrical components, including inverters and transformers, are expected to cost Tk 732.25 crore. These systems are central to converting solar energy into electricity that can be transmitted through the grid.

The Infrastructure Investment Facilitation Company has completed a favourable feasibility assessment for the project. Its development also fits within Sustainable Development Goal 7, which focuses on access to affordable, reliable, sustainable and modern energy.

A Larger National Renewable Energy Push

Rampal is part of a wider national programme focused on rooftop solar expansion and the development of renewable-energy entrepreneurs. Bangladesh has on-grid generation capacity of 29,143MW, while solar accounts for 1,642.7MW of that total.

Adding 442MW at a single site would provide a notable increase in the country’s solar portfolio. It would also support the government’s goal of obtaining 20 percent of electricity from renewable sources by 2030.

The project’s significance extends beyond its technical capacity. It represents a shift in the planned use of strategically acquired land, moving it from a coal-oriented development path toward clean-energy generation. For Rampal, the proposed solar plant could become a major example of how existing power-sector assets can be adapted to meet Bangladesh’s changing energy priorities.

If the project reaches its 2029 operational target, the facility will combine large-scale solar generation, battery storage and new transmission infrastructure at a location already closely associated with national power development. The result could help strengthen renewable capacity while supporting a more diverse and resilient electricity system.

Related Reading

Frequently Asked Questions

What is Rampal to turn into Tk 2 498cr?

Rampal to turn into Tk 2 498cr is the main topic of this guide. The article explains the context, practical details, and next steps readers should understand.

Why does Rampal to turn into Tk 2 498cr matter?

Rampal to turn into Tk 2 498cr matters because readers are looking for a useful answer, not just a short summary. Good content should match search intent and help them decide what to do next.